Construction Updates:

Demolition of the Bull Test facility and Feed Lot began on Jan. 2, 2006. The original sites are now covered with several feet of soil thanks to the work of earthmovers and bulldozers who are literally moving mountains and filling in valleys.

"Feed Mill Road" is about to become a memory. In order for demolition preparations to get started, the remaining facilities were vacated on April 30.

Extra equipment from the Feed Mill, Abattoir, and Farrier Building was sold at a successful surplus sale.

In mid-June demolition crews to began dismantling these structures. Then the earth moving equipment will transform the area too.

The Animal Science Department is quite fortunate to have retired professor Jim Flanagan photographing the demolition of former facilities and the construction of new facilities. Be sure to check the Animal Science Web site and Stock Report issues for pictures and updates.

Facility Relocation and Renovation Update